Simmons Library Renovation
Projected Timeline - subject to change
- Interim Library opens in Lefavour June ‘04
- Beatley Building demo-ed: June-August ‘04
- New building construction starts: Sept ‘04
- New building completed: Dec ‘05
- New building ready for occupancy: Jan‘06
- Lefavour
interior renovations and new Library: expected AY ’06 through
AY '08, depending on MP III funding and phasing
The Library Renovation Team is eager to hear your ideas, concerns
and comments throughout the planning process, and as construction
progresses. For questions/comments about the project, contact Daphne
Harrington (2754), Library Director.